Project Execution

Approach

Both the EDP and Main Plant /KKV phases of the project are brown-field expansions of the existing heap leach-solvent extraction-electrowinning operation.

The project execution is based on an Engineering, Procurement and Construction Management (EPCM) philosophy with engineering managed by Electrowin Pty Ltd and NeuBau Pty Ltd and procurement and construction managed by Finders.

Resindo, an Indonesian EPCM contractor will provide inspection and project controls support.

Karridale, a Western Australian contractor, will provide construction management support at site for the re-installation of theWhim Creek plant.

PT SDV Logistics are engaged to relocate the Whim Creek SX-EW Plant from Western Australia and to consolidate the other equipment and materials in Surabaya for transport to Wetar.

Specialist contractors will be used for structural-mechanical-piping (PT Supra Surya Indo) and electrical and instrumentation (E&I) installation (O'Donnell Griffin Indonesia, ODG). ODG was responsible for E&I on the demonstration plant.

Commissioning engineers will be provided by Australian company PPM Solutions which was responsible for commissioning of the original demonstration plant.

Schedule

The total construction project duration is 24 months. Assuming timely project finance and permitting, first cathode production from the EDP is 10 months from project start while first cathode production from the Main Plant is scheduled 20 months from project start.

Key milestone dates from the project schedule are:

Q3
2011
Q4
2011
Q1
2012
Q2
2012
Q3
2012
Q4
2012
Q1
2013
Q2
2013
Q3
2013
Project Approvals
Project Finance
Mining of first ore, re-start Demo Plant
Mobilisation of heavy equipment contractors
Commence civil works
First EDP copper production
Commissioning of EDP Neutralisation Plant
First stacking to Gold Pit heap leach
First Main Plant copper production
Commissioning of KKV Neutralisation Plant
First stacking to KKV heap leach